S.C.R. WAGON WORK SHOP, GUNTUPALLI

                  JET CLEANING MACHINE FOR CONES

PREVENTIVE MAINTENANCE SCHEDULES of Cone Assembly Cleaning Machine

Monthly:

     1. Check the condition of domes visually for any crack and replace if necessary.
     2. Clean the nozzles of the system.
     3. Check the condition of the bearings and lubricated them.
     4. Check the V- belt tension physically and adjust / replace as per requirement.
     5. Observe for any unusual sounds.
     6. Check for any leakages in the pipe line and if required arrest it.
     7. Check the flow of the oil from the nozzles spray visually.
     8. Clean the filter and replace if required.
     9. Check the oil for sludge and clean if required.

Yearly:

     1. Check the working of the pump, if required overhaul it.
     2. Check the wear and tear of the running shaft.
     3. Check the condition of hydraulic hose pipes [1/2”x 750 mm length with ½” female swivel nut],
        replace if necessary.
     4. Check the condition of key ways and pulleys of the shaft and replace if required.